It was time to locate a new site. I was fortunate enough to find a factory construction site in East Keilor in the factory district. I happened to stumble upon this site, as it is on a road that veers off the road that gets me home from university each day. This factory was harder than the last to get a hold of, as the contractor was difficult to contact. However, after much patience, I was able to negotiate a time to access the site and witness the erection of pre-cast concrete panels.
Tuesday, April 22, 2008
construction familiarisation_visit four
Week_5: Tutorial Task

Tutorial Task:
This week we were asked to complete a pre-cast and tilt-up concrete construction detail. Here, I had to add the purlins which ran across the page, a pre-cast load-bearning panel which was seperated from the slab using a mastic, and an angle which was used to connect the wall with the purlins.
Wednesday, April 2, 2008
Week_4: Tutorial Task

Tutorial Task:
Following the lecture regarding concrete construction, we were given the task in class to complete a pre-cast concrete construction detail, portraying a pre-cast wall. Here, i had to add the Bondek beneath the box-gutter, the concrete pad footing, the mastic that seperates the wall from the slab. Typical additions of the C-purlins with insulation and safety mesh were also included. I learned through this lesson that pad footings actually transfer load into the bedrock below, which is far beneficial that having it transferred through unstable soils.
Week_3: Tutorial Task
Construction Familiarisation_visit three
After an inspection by the Council Building Inspector, the Contractor
gives the all clear to commence the pouring of the slab.
All formwork was eventaully removed and, once it was cured, the concrete was treated with a non-stick concrete releasing agent, called 'Bond Breaker.' The agent gave the slab surface a red complextion.
Construction familiarisation_visit two
Reinforcement starter bars were added to the trench, which were to be eventually set into the concrete slab.
Construction familiarisation_visit one
Over the Easter holidays I was able to locate a proposed pre-cast factory under construction in Airport West, West Melbourne. After recieving permission by the site foreman, I was able to wander around the site and familiarise myself with commercial construction.